top of page
Search

Weekend Update!

So in unusually dry conditions for a change albeit a bit chilly, work continued on the water and oil systems!

The overhauled oil cooler was refitted along with its associated pipework, the overhauled water pump was put on the loco ready for next Saturdays working party, the contaminated oil was removed as well. During a small few breaks, 714 got a bit of a clean, you can clearly see by looking at the nose end what's clean and what isn't...

Next week, the water pump will be refitted some clean old oil out in, and hopefully we will be able to run the loco up to check the systems. Once satisfied all is well, new oil will be uploaded along with new oil filters.


So far the work is on track ready to be completed in time for our trip to Loram to change the traction motor!

That’s all for this week. We thank you all for your support. Have a good week!


Heavy tractor group.



 
 
 

Recent Posts

See All
Early weekend update

This week, 37714 had the traction motors disconnected, the brake pipes and AWS disconnected and the sanders removed, in preparation for the trip on Thursday to Loram to replace No. 2 traction motor. S

 
 
 
Saturday Update!

Today saw the final push to get 714 back together, First job saw all the relays and contactors get a good clean and spray of magic electrical stuff apparently. The old oil and filters removed and new

 
 
 

Comments


bottom of page